Build Fastest
Given a project requirement, Intel Accelerator determines the modular architecture, the qualified supplier combination and the earliest realistic ready-for-service date.
Project requirement
Demo scenario. Editable requirement intake arrives with the AI Planner in Phase 2.
Fastest credible infrastructure plan
3 × 150 MVA main transformers → 10 × 10 MW prefabricated MV e-houses → 2N UPS at 1.5 MW module granularity → busway to data hall.
8 × 8 MW modular heat rejection plants → primary loop → 24 × 2.5 MW Coolant Distribution Units (N+1) → secondary loop → manifolds → cold plates.
10 MW electrical blocks and 5 MW cooling blocks. Parallel factory/site construction, repeatable commissioning, phased energization from block 1.
Recommended supplier combination
| Scope | Supplier | Lead time | Basis |
|---|---|---|---|
| Transformers | Nordpower Transformers | 132wCRITICAL | Monterrey slot, cancelled order |
| MV switchgear | Arcline Power Systems | 58wSEVERELY CONSTRAINED | Houston line, UL 1558 |
| Modular power | Arcline Power Systems | 30wCONSTRAINED | 10 MW e-house blocks |
| UPS | Voltbank Energy Storage | 28wCONSTRAINED | Technical validation required |
| Generation | Helion Rotating Power | 60wSEVERELY CONSTRAINED | Delivered history 71w — buffer applied |
| Heat rejection | Cryomax Heat Rejection | 34wCONSTRAINED | Charlotte plant |
| CDU | Thermaflux Liquid Cooling | 20wNORMAL | Austin, 12 slots open |
| Racks & QD | Multiple qualified | 14wNORMAL | No material constraint |
Combination is optimized for compliance, speed, reliability, landed cost and risk — not lowest unit price. Interoperability between the e-house and UPS selection requires engineering sign-off.
How to build faster
- AAlternative transformer supplier (Monterrey slot)≈ 12 weeksModerate — requires technical validationMEDIUM
- BModular power architecture (10 MW e-house blocks)≈ 22 weeksLow — supplier has US UL-certified lineHIGH
- CReserved manufacturing slot (cancelled order)≈ 18 weeksModerate — slot expires in 30 daysHIGH
- DPhased energization (20 MW first block)First capacity ≈ 9 months earlierLow — requires utility agreementMEDIUM
- ESecondary-market transformer≈ 30 weeksHigh — condition and warranty unverifiedLOW
Procurement priority
- Main power transformer 150 MVAORDER NOW
- MV switchgear line-upORDER NOW
- UPS module 1.5 MWHIGH
- 3 MW standby generatorHIGH
- Coolant Distribution Unit 2.5 MWHIGH
- Modular heat rejection plant 8 MWHIGH
Unknowns & validation required
- Utility energization date — SUPPLIER CONFIRMATION REQUIRED
- UPS interoperability with selected e-house controls — DATA REQUIRED
- Generator emissions permit path in Taylor County — DATA REQUIRED
- Secondary-market transformer condition report — DATA REQUIRED
- Site crane / heavy-lift window for 10 MW e-houses — DATA REQUIRED
Supplier risk on this plan
- Nordpower TransformersNEURA SCORE 849LOWSOURCE Manufacturer quotation 2026-07-28LEVEL A · Verified directLAST VERIFIED 2026-07-28HIGH
- Arcline Power SystemsNEURA SCORE 8813LOWSOURCE NEURA procurement recordLEVEL A · Verified directLAST VERIFIED 2026-08-04VERY HIGH
- Thermaflux Liquid CoolingNEURA SCORE 9112LOWSOURCE Supplier confirmationLEVEL A · Verified directLAST VERIFIED 2026-08-05VERY HIGH
- Modulus InfrastructureNEURA SCORE 8617LOWSOURCE Supplier submitted profileLEVEL D · Market intelligenceLAST VERIFIED 2026-06-19MEDIUM
- Helion Rotating PowerNEURA SCORE 7626MODERATESOURCE Industry contactLEVEL D · Market intelligenceLAST VERIFIED 2026-04-08LOW