Global product intelligence library
Product Library
Search any infrastructure component by manufacturer, model, category, capacity, voltage, certification, region or lead time. Sources, owners and access levels are shown on every record.
30 product records
Vertiv — XDU 1350
Cooling · Coolant distribution unit · Liquid cooling
PUBLICDATA COMPLETENESS 69%
Capacity 1.35 MWLead time 24–32 weeksRegions North America, EMEA, APACCertification UL, CEVersions 2Documents 3Factories Westerville, United States · Tognana, Italy
Vertiv — XDU 070
Cooling · Coolant distribution unit · Liquid cooling
PUBLICDATA COMPLETENESS 83%
Capacity 0.07 MWLead time 12–18 weeksRegions North America, EMEA, APACCertification UL, CEVersions 1Documents 2Factories Westerville, United States
Motivair — MCDU 2500
Cooling · Coolant distribution unit · Liquid cooling
PUBLICDATA COMPLETENESS 92%
Capacity 2.5 MWLead time 20–28 weeksRegions North America, EMEACertification ULVersions 1Documents 2Factories Amherst, United States
Boyd — CDU-1300
Cooling · Coolant distribution unit · Liquid cooling
PUBLICDATA COMPLETENESS 90%
Capacity 1.3 MWLead time 18–26 weeksRegions North America, APACCertification ULVersions 1Documents 2Factories Portland, United States
CoolIT Systems — CHx1000
Cooling · Coolant distribution unit · Liquid cooling
PUBLICDATA COMPLETENESS 90%
Capacity 1 MWLead time 16–24 weeksRegions North America, EMEA, APACCertification UL, CEVersions 1Documents 2Factories Calgary, Canada
Stulz — CyberCool CDU
Cooling · Coolant distribution unit · Liquid cooling
PUBLICDATA COMPLETENESS 89%
Capacity 1.2 MWLead time 22–30 weeksRegions EMEA, APACCertification CEVersions 1Documents 2Factories Hamburg, Germany
Siemens Energy — GEAFOL / oil-immersed class
Power · Large power transformer · Transformers
PUBLICDATA COMPLETENESS 73%
Capacity 60 MVALead time 104–156 weeksRegions EMEA, North America, APACCertification IEC, IEEEVersions 1Documents 2Factories Nuremberg, Germany · Weiz, Austria
Siemens Energy — GEAFOL 2500
Power · Medium voltage transformer · Transformers
PUBLICDATA COMPLETENESS 90%
Capacity 2.5 MVALead time 36–52 weeksRegions EMEA, APAC, North AmericaCertification IEC, CEVersions 2Documents 2Factories Kirchheim, Germany
Hitachi Energy — TrafoStar class
Power · Large power transformer · Transformers
PUBLICDATA COMPLETENESS 89%
Capacity 100 MVALead time 120–168 weeksRegions EMEA, North America, APACCertification IEC, IEEEVersions 1Documents 2Factories Ludvika, Sweden
Schneider Electric — PIX / SM AirSeT
Power · MV switchgear · Medium voltage
PUBLICDATA COMPLETENESS 90%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 40–60 weeksRegions EMEA, North America, APACCertification IEC, CEVersions 1Documents 2Factories Grenoble, France · Smyrna, United States
ABB — UniGear ZS1
Power · MV switchgear · Medium voltage
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 36–56 weeksRegions EMEA, APAC, North AmericaCertification IECVersions 1Documents 2Factories Ratingen, Germany · Xiamen, China
Eaton — Pow-R-Way III
Power · Busway · Low voltage
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 18–28 weeksRegions North America, EMEACertification ULVersions 1Documents 2Factories Cleveland, United States
Vertiv — Liebert Trinergy Cube
Power · UPS · Critical power
PUBLICDATA COMPLETENESS 100%
Capacity 3.4 MWLead time 26–38 weeksRegions EMEA, APACCertification CE, IECVersions 2Documents 2Factories Bologna, Italy
Schneider Electric — Galaxy VX
Power · UPS · Critical power
PUBLICDATA COMPLETENESS 100%
Capacity 1.5 MWLead time 24–34 weeksRegions North America, EMEA, APACCertification UL, CEVersions 2Documents 2Factories Barcelona, Spain · O'Fallon, United States
Caterpillar — C175-20
Power · Generator · Standby power
PUBLICDATA COMPLETENESS 89%
Capacity 3 MWLead time 40–64 weeksRegions North America, EMEA, APACCertification UL, EPA Tier 2Versions 1Documents 2Factories Lafayette, United States
Cummins — QSK95
Power · Generator · Standby power
PUBLICDATA COMPLETENESS 100%
Capacity 3.5 MWLead time 44–70 weeksRegions North America, EMEA, APACCertification ULVersions 1Documents 2Factories Seymour, United States
Tesla — Megapack 2 XL
Power · BESS · Energy storage
PUBLICDATA COMPLETENESS 100%
Capacity 3.9 MWhLead time 40–60 weeksRegions North America, EMEA, APACCertification UL 9540AVersions 1Documents 2Factories Lathrop, United States · Shanghai, China
Trane — Sintesis RTAF
Cooling · Chiller · Chillers
PUBLICDATA COMPLETENESS 78%
Capacity 1.6 MWLead time 26–40 weeksRegions North America, EMEACertification AHRI, CEVersions 1Documents 2Factories Charmes, France · Pueblo, United States
Munters — SyCool Dry
Cooling · Dry cooler · Heat rejection
PUBLICDATA COMPLETENESS 89%
Capacity 1.2 MWLead time 20–30 weeksRegions EMEA, North AmericaCertification CEVersions 1Documents 2Factories Tobo, Sweden
Baltimore Aircoil — Series 3000
Cooling · Cooling tower · Heat rejection
PUBLICDATA COMPLETENESS 100%
Capacity 3 MWLead time 18–28 weeksRegions North America, EMEACertification CTIVersions 1Documents 2Factories Baltimore, United States
Grundfos — NK / NKG
Cooling · Pump · Hydronics
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 10–18 weeksRegions EMEA, APAC, North AmericaCertification CEVersions 1Documents 2Factories Bjerringbro, Denmark
Alfa Laval — T-series
Cooling · Plate heat exchanger · Heat transfer
PUBLICDATA COMPLETENESS 88%
Capacity 5 MWLead time 12–20 weeksRegions EMEA, APAC, North AmericaCertification PED, ASMEVersions 1Documents 2Factories Lund, Sweden
Parker — UQD series
Cooling · Quick disconnect · Liquid cooling
PUBLICDATA COMPLETENESS 88%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 8–14 weeksRegions North America, EMEA, APACCertification OCP UQDVersions 1Documents 2Factories Minneapolis, United States
nVent — Liquid cooling manifold
Cooling · Manifold · Liquid cooling
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 10–16 weeksRegions North America, EMEACertification ULVersions 1Documents 2Factories Anoka, United States
Vertiv — VR / DCE high density
Data hall · Rack · Racks
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 8–14 weeksRegions North America, EMEA, APACCertification ULVersions 1Documents 2Factories Westerville, United States
Legrand — Raritan PX3
Data hall · Rack PDU · Rack power
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 10–16 weeksRegions North America, EMEA, APACCertification UL, CEVersions 1Documents 2Factories Somerset, United States
Schneider Electric — EcoStruxure Modular
Modular · Prefabricated data hall · Modular systems
PUBLICDATA COMPLETENESS 100%
Capacity 2 MWLead time 30–48 weeksRegions EMEA, North America, APACCertification CE, ULVersions 1Documents 2Factories Barcelona, Spain · Bangalore, India
ABB — E-House
Modular · E-house · Modular systems
PUBLICDATA COMPLETENESS 88%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 34–52 weeksRegions EMEA, APAC, North AmericaCertification IEC, CEVersions 1Documents 2Factories Genoa, Italy
Siemens — Desigo CC
Controls · BMS · Controls
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 8–16 weeksRegions EMEA, North America, APACCertification CEVersions 1Documents 2Factories Zug, Switzerland
Schneider Electric — EcoStruxure Power Monitoring Expert
Controls · EPMS · Controls
PUBLICDATA COMPLETENESS 100%
Capacity NOT AVAILABLE IN CURRENT SOURCELead time 8–14 weeksRegions EMEA, North America, APACCertification CEVersions 1Documents 2Factories Grenoble, France