Lead-time intelligence engine

Lead Times

Lead time is time-series data. Old values are never overwritten. Manufacturer quote, distributor estimate, market estimate, NEURA estimate and actual delivered time are stored separately.

Demo data

Category lead times

CategoryCurrent3 mo6 mo12 moTrend 12 moQualified suppliersSource
Large Power Transformers
D · Power
148wCRITICAL142w136w118w+30w14LEVEL A · 2026-07-28
Gas Turbines
K · Generation
210wCRITICAL205w190w160w+50w5LEVEL B · 2026-06-14
MV Switchgear
E · Power
74wSEVERELY CONSTRAINED78w82w70w+4w26LEVEL A · 2026-08-02
Diesel Generators (≥3MW)
J · Generation
62wSEVERELY CONSTRAINED66w70w58w+4w18LEVEL D · 2026-07-11
Coolant Distribution Units (CDU)
R · Liquid cooling
24wNORMAL26w22w18w+6w31LEVEL A · 2026-08-05
Chillers (>1000 TR)
O · Cooling
46wCONSTRAINED44w40w36w+10w12LEVEL C · 2026-05-30
UPS (≥1.5MW modules)
G · Power
30wCONSTRAINED34w38w40w-10w21LEVEL A · 2026-07-22
Busway
H · Power
20wNORMAL22w24w20wflat17LEVEL D · 2026-07-04
Quick Disconnects
V · Liquid cooling
14wNORMAL18w26w30w-16w9LEVEL A · 2026-08-01
Racks & Enclosures
AD · White space
10wFAST10w12w14w-4w44LEVEL A · 2026-08-06
IMMEDIATE <4wFAST 4–12wNORMAL 13–26wCONSTRAINED 27–52wSEVERELY CONSTRAINED 53–104wCRITICAL >104wThresholds administrator-configurable.

Large Power Transformers

Aug 25 · 118wNov 25 · 126wFeb 26 · 136wMay 26 · 142wAug 26 · 148w
SOURCE Manufacturer quotations (n=6)LEVEL A · Verified directLAST VERIFIED 2026-07-28HIGH

MV Switchgear

Aug 25 · 70wNov 25 · 80wFeb 26 · 82wMay 26 · 78wAug 26 · 74w
SOURCE Distributor quotationsLEVEL A · Verified directLAST VERIFIED 2026-08-02HIGH

Coolant Distribution Units (CDU)

Aug 25 · 18wNov 25 · 20wFeb 26 · 22wMay 26 · 26wAug 26 · 24w
SOURCE Supplier confirmations (n=9)LEVEL A · Verified directLAST VERIFIED 2026-08-05VERY HIGH

UPS (≥1.5MW modules)

Aug 25 · 40wNov 25 · 39wFeb 26 · 38wMay 26 · 34wAug 26 · 30w
SOURCE Manufacturer quotationLEVEL A · Verified directLAST VERIFIED 2026-07-22HIGH