RFS PROTECTION

Multi-source resilience

Every critical package carries a primary, secondary and backup source. Change a source and the concentration risk, drop-in score and schedule exposure update with it.

Demo data
TARGET RFS
June 2028
CURRENT FORECAST
August 2028
SLIP
8 weeks
RFS CONFIDENCE
62%

Top risks — primary delay: MV switchgear

MV switchgear
58 week quoted lead vs 50 weeks available.
Standby generator
72 week primary; secondary source recovers 8 weeks.
CDU
Second source qualified; slot confirmation pending.
Quick disconnects
Small item, controls rack fit-out start.
Busway
Within float.

Single-source concentration risk

Vertiv
UPS · Coolant distribution unit (CDU)
20% of critical packages
LOWQUALIFY SECOND SOURCE
Siemens Energy
Medium voltage transformer
10% of critical packages
LOWQUALIFY SECOND SOURCE
Schneider Electric
MV switchgear
10% of critical packages
LOWQUALIFY SECOND SOURCE
CPC (Colder)
Quick disconnects (QD)
10% of critical packages
LOWQUALIFY SECOND SOURCE
Trane
Chiller / heat rejection
10% of critical packages
LOWQUALIFY SECOND SOURCE
Caterpillar
Standby generator
10% of critical packages
LOWQUALIFY SECOND SOURCE
Starline
Busway / power distribution
10% of critical packages
LOWQUALIFY SECOND SOURCE
nVent
Liquid-ready rack / enclosure
10% of critical packages
LOWQUALIFY SECOND SOURCE
Siemens
Controls / BMS integration
10% of critical packages
LOWQUALIFY SECOND SOURCE
Portfolio second-source readiness: 93%

CRITICAL PACKAGES — PRIMARY / SECONDARY / BACKUP

Medium voltage transformer
POWER · CRITICAL · ON SITE 26 WEEKS BEFORE RFS
80%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
MV switchgear
POWER · CRITICAL · ON SITE 24 WEEKS BEFORE RFS
98%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
UPS
POWER · HIGH · ON SITE 18 WEEKS BEFORE RFS
98%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
Coolant distribution unit (CDU)
TCS · CRITICAL · ON SITE 16 WEEKS BEFORE RFS
98%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
Quick disconnects (QD)
TCS · HIGH · ON SITE 10 WEEKS BEFORE RFS
80%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
Chiller / heat rejection
COOLING · HIGH · ON SITE 20 WEEKS BEFORE RFS
98%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
Standby generator
POWER · HIGH · ON SITE 22 WEEKS BEFORE RFS
98%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
Busway / power distribution
POWER · MEDIUM · ON SITE 12 WEEKS BEFORE RFS
98%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
Liquid-ready rack / enclosure
DATA HALL · MEDIUM · ON SITE 10 WEEKS BEFORE RFS
98%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT
Controls / BMS integration
CONTROLS · MEDIUM · ON SITE 8 WEEKS BEFORE RFS
80%
SECOND-SOURCE READINESS
BRAND RULEGET 3 QUOTESCHECK SLOT

SUBSTITUTION ANALYSIS — DROP-IN MATCH SCORE

INTERFACECURRENTALTERNATIVEVERDICT
Capacity1.35 MW2.5 MWMINOR REVIEW
Flow≈ 1,100 L/min≈ 1,900 L/minMINOR REVIEW
Pressure ratingPN10PN10NO CHANGE
Supply voltage400 V / 3 ph400 V / 3 phNO CHANGE
Frequency50 Hz50 HzNO CHANGE
Approach temperature≈ 3 K≈ 3 KNO CHANGE
CoolantPG25 / waterPG25 / waterNO CHANGE
Secondary connectionDN100 flangeDN100 flangeNO CHANGE
Controls protocolBACnet / ModbusBACnet / ModbusNO CHANGE
CertificationCE / ULUL (CE confirm)MINOR REVIEW
FootprintConfirm with providerConfirm with providerMINOR REVIEW

RESCUE MY SCHEDULE — SEARCH ORDER

Ten recovery strategies, searched in order

1
Same manufacturer, alternate model
Uprated or de-featured model already in production.
28 wks recoveryIMPACT LOW
2
Same manufacturer, alternate factory
Shift build to a plant with open capacity in another region.
412 wks recoveryIMPACT LOW
3
Distributor / channel inventory
Stock held by authorised distribution instead of a new build slot.
824 wks recoveryIMPACT MEDIUM
4
Compatible alternative manufacturer
Run substitution analysis and qualify a drop-in equivalent.
620 wks recoveryIMPACT MEDIUM
5
Regional supplier
Local build reduces logistics and customs exposure.
414 wks recoveryIMPACT MEDIUM
6
Global supplier
Widen search outside the project region where certification allows.
416 wks recoveryIMPACT MEDIUM
7
Available or cancelled factory slot
Take over a released production slot listed on the platform.
1030 wks recoveryIMPACT MEDIUM
8
Secondary market
Only where provenance, warranty and certification can be evidenced.
1240 wks recoveryIMPACT HIGH
9
Alternative module architecture
Change topology so the constrained item is no longer on the critical path.
826 wks recoveryIMPACT HIGH
10
Phased deployment
Energise partial capacity at RFS and complete the remainder later.
1252 wks recoveryIMPACT HIGH