Envision Galaxy Ulanqab
Address not published · China
IT power
118 MW
Compute
48k H100-eq
Capex
$4.5B
- Owner
- —
- City
- —
- Country
- China
- Accelerators deployed
- Ascend 950PR
- Buildings operational
- 4
- Programme
- NA
- Construction / EPC
- NA
- Energy partners
- NA
Used by (companies)
No public tenant disclosure
Latest deployment milestone · 2027-12-01
Building 4 expected to be fully operational, assuming a 3-month fitout period after taking one year from land clearing to commissioning as demonstrated by Building 1.