Google Mesa
Address not published · United States
IT power
183 MW
Compute
290k H100-eq
Capex
$6.9B
- Owner
- Google #confident
- City
- —
- Country
- United States
- Accelerators deployed
- TPU v6e,TPU v5p
- Buildings operational
- 2
- Programme
- NA
- Construction / EPC
- NA
- Energy partners
- NA
Used by (companies)
No public tenant disclosure
Latest deployment milestone · 2026-08-15
Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.
SOURCE Epoch AI · AI Data Centers · LEVEL A · LAST VERIFIED 2026-09-24
SUPPLY-SIDE INTELLIGENCE GAPS FOR THIS SITE
- · Equipment packages and suppliers — not published for this site
- · Cooling architecture and rack density — needs confirmation
- · MEP module provider — not known
- · Substation and interconnection detail — utility filing review required