Verified project registry · refreshed daily
Google Waltham Cross
Land at Maxwell's Farm West, Great Cambridge Road, Cheshunt, EN8 8XH · United Kingdom
IT power
88 MW
Compute
124k H100-eq
Capex
$3.3B
- Owner
- Google #confident
- City
- Cheshunt
- Country
- United Kingdom
- Accelerators deployed
- TPU v6e
- Energy partners
- Shell Energy EuropeEngie
- Buildings operational
- 1
- Programme
- NA
- Construction / EPC
- NA
Used by (companies)
Google DeepMind #speculative
Latest deployment milestone · 2026-04-23
Full buildout reconfirmed via high-resolution Pléiades-Neo satellite image; no capacity change since September 2025.
SOURCE Epoch AI · AI Data Centers · LEVEL A · LAST VERIFIED 2026-09-24
SUPPLY-SIDE INTELLIGENCE GAPS FOR THIS SITE
- · Equipment packages and suppliers — not published for this site
- · Cooling architecture and rack density — needs confirmation
- · MEP module provider — not known
- · Substation and interconnection detail — utility filing review required