Huawei Horinger
Huawei, Horinger, China · China
IT power
170 MW
Compute
81k H100-eq
Capex
$6.4B
- Owner
- Huawei #confident
- City
- Horinger
- Country
- China
- Accelerators deployed
- Ascend 910C,Ascend 910B
- Buildings operational
- 5
- Programme
- NA
- Construction / EPC
- NA
- Energy partners
- NA
Used by (companies)
No public tenant disclosure
Latest deployment milestone · 2028-02-17
Building 6 (South Zone) is operational (estimate). This was the only new building under construction as of August 2026. We estimate the operational date based on an average of (1) previous buildings taking about 2 years on average from starting the building shell to becoming operational at ~full capacity, (2) a similar building at the Huawei Wuhu campus taking an estimated 550 days to become fully operational. Building 6 can reportedly support 100,000 AI accelerator cards and will deploy Huawei Ascend 950 chips. Based on the timing, we assume it has capacity for 100,000 Ascend 950DT chips (Asc
SOURCE Epoch AI · AI Data Centers · LEVEL A · LAST VERIFIED 2026-11-08
SUPPLY-SIDE INTELLIGENCE GAPS FOR THIS SITE
- · Equipment packages and suppliers — not published for this site
- · Cooling architecture and rack density — needs confirmation
- · MEP module provider — not known
- · Substation and interconnection detail — utility filing review required