40 MVA modular substation, IEC 61439
Modular substation + transformer skids · Data required
46wCONSTRAINED
- Supplier
- Gridforge Substations
- Project
- Rheinland AI Cluster
- End user
- Undisclosed EU hyperscaler (LOI, 46 MW IT)
- Quantity
- 2 substations
- MW served
- 60 MW
- Factory
- Gdansk, PL
- Quoted lead time
- 46 weeks
- Commercial value
- Data required
- Current stage
- TENDER
- Manufacturing start
- NA
- FAT date
- NA
- SAT date
- NA
Milestone chain
Award / PO
2027-10-04
Ship
2028-08-21
On site
2028-09-18
Energization
Q3 2029
SOURCE Broker informationLEVEL D · Market intelligenceLAST VERIFIED 2026-02-17UNVERIFIED