Demo project record · simulated

Rheinland AI Cluster

Cologne, Germany · Nordfeld Capital · Permitting
Campus / IT
60 / 46 MW
Target RFS
Q1 2029
Forecast
Q3 2029
Readiness
54%
Critical path
Grid connection + transformers
Cooling architecture
DLC 70% / air 30%
End user
Undisclosed EU hyperscaler (LOI, 46 MW IT)
Customer type
Hyperscale cloud
Workload / density
Mixed training + enterprise cloud, 80 kW/rack
Offtake
Letter of intent — lease not executed
Utility / grid
Amprion / Westnetz — 110 kV, connection study in progress
Substation installed
2 × 40 MVA (80 MVA planned)
EPC / main contractor
Not awarded — EPC tender Q1 2027
Location
Germany
SOURCE Government filingLEVEL B · Primary publicLAST VERIFIED 2026-06-25MEDIUM

Phased deployment

Phase 124 MWQ3 2029Permitting
Phase 236 MWQ1 2030Concept

Supplier packages (4)

SupplierEquipmentQtyMWFactoryAwardEnergizationStage
Nordpower Transformers40 MVA, 110/20 kV2 units60Vaasa, FI2026-09-14Q3 2029TENDEROpen
Gridforge Substations40 MVA modular substation, IEC 614392 substations60Gdansk, PL2027-10-04Q3 2029TENDEROpen
Thermaflux Liquid Cooling2.5 MW L2L CDU14 CDUs32Taoyuan, TW2028-08-07Q3 2029TENDEROpen
Cryomax Heat Rejection1000+ TR chillers + dry coolers6 units14Milan, IT2028-03-13Q3 2029TENDEROpen