Nordpower Transformers
Vaasa, Finland · Transformer manufacturer · APPROVED
Provider score
84
- Quoted lead time
- 132 weeks
- Actual delivered
- 141 weeks
- Next production slot
- Q1 2028 (Monterrey)
- Certifications
- IEC 60076, IEEE C57, ISO 9001
- Technical
- 88/100
- Reliability
- 91/100
- Commercial
- 76/100
- Service
- 80/100
Equipment categories supplied
This is a demonstration record used to exercise the intelligence model. Verified provider dossiers live in MEP modular providers. Related categories: TransformersModular substations
NVIDIA ecosystem
NO NVIDIA REFERENCE FOUND for this company in the indexed public sources.
NVIDIA references shown in Intel Accelerator are sourced from publicly available NVIDIA ecosystem information. Presence of an NVIDIA reference does not imply endorsement of Intel Accelerator, and Intel Accelerator is not affiliated with, sponsored by or certified by NVIDIA.
Brands & product marques
No brand architecture captured for this company yet.
Locations & factories (2)
Past projects / reference projects
| Project | Equipment | MW | Factory | Award | Stage | |
|---|---|---|---|---|---|---|
| Lone Star AI Campus | 150 MVA, 345/34.5 kV ONAN/ONAF | 100 | Monterrey, MX | 2026-03-16 | IN PRODUCTION | Open |
| Rheinland AI Cluster | 40 MVA, 110/20 kV | 60 | Vaasa, FI | 2026-09-14 | Open |
Available capacity from this supplier
Appears in reference BOM
- Main power transformer 150 MVA — 3 · Power block (10 × 5 MW) · 132w · ORDER NOW
Related signals
No monitored signal recorded for this company in the current window.
Evidence
SOURCE Manufacturer quotation 2026-07-28LEVEL A · Verified directLAST VERIFIED 2026-07-28HIGH