150 MVA, 345/34.5 kV ONAN/ONAF
Main power transformers · USD 26.7M (3 units, indicative)
132wCRITICALIN PRODUCTION
- Supplier
- Nordpower Transformers
- Project
- Lone Star AI Campus
- End user
- Vantix AI (anchor tenant, 78 MW IT)
- Quantity
- 3 units
- MW served
- 100 MW
- Factory
- Monterrey, MX
- Quoted lead time
- 132 weeks
- Commercial value
- USD 26.7M (3 units, indicative)
- Current stage
- IN PRODUCTION
- Manufacturing start
- NA
- FAT date
- NA
- SAT date
- NA
Milestone chain
Award / PO
2026-03-16
Ship
2028-09-25
On site
2028-10-30
Energization
Q2 2029
SOURCE Manufacturer quotation 2026-07-28LEVEL A · Verified directLAST VERIFIED 2026-07-28HIGH