Demo project record · simulated

Lone Star AI Campus

Abilene, Texas, USA · Meridian Digital · Detailed design
Campus / IT
100 / 78 MW
Target RFS
Q4 2028
Forecast
Q2 2029
Readiness
72%
Critical path
Large power transformers
Cooling architecture
DLC 85% / air 15%
End user
Vantix AI (anchor tenant, 78 MW IT)
Customer type
AI model developer
Workload / density
GPU training clusters, 132 kW/rack DLC
Offtake
15-year triple-net lease, full campus pre-let
Utility / grid
Oncor — 345 kV interconnection, queue position confirmed
Substation installed
3 × 150 MVA (450 MVA installed)
EPC / main contractor
Meridian Build Group (self-perform) + Arcline power packages
Location
USA
SOURCE Utility interconnection filingLEVEL B · Primary publicLAST VERIFIED 2026-07-30HIGH

Phased deployment

Phase 140 MWQ4 2028Detailed design
Phase 235 MWQ2 2029Design
Phase 325 MWQ4 2029Concept

Supplier packages (5)

SupplierEquipmentQtyMWFactoryAwardEnergizationStage
Nordpower Transformers150 MVA, 345/34.5 kV ONAN/ONAF3 units100Monterrey, MX2026-03-16Q2 2029IN PRODUCTIONOpen
Arcline Power Systems38 kV arc-resistant line-ups + 10 MW e-house skids10 line-ups100Houston, US2026-06-01Q4 2028AWARDEDOpen
Thermaflux Liquid Cooling2.5 MW L2L CDU, N+1 pumps (85% DLC scope)24 CDUs + 624 manifold sets66Austin, US2027-11-05Q4 2028TENDEROpen
Cryomax Heat Rejection8 MW modular dry cooler + adiabatic plant8 plants64Charlotte, US2027-06-18Q4 2028TENDEROpen
Helion Rotating Power3 MW diesel gensets, EPA Tier 412 units36Pune, IN2027-01-22Q4 2028TENDEROpen