3 MW diesel gensets, EPA Tier 4
Standby generation · Data required
60wSEVERELY CONSTRAINED
- Supplier
- Helion Rotating Power
- Project
- Lone Star AI Campus
- End user
- Vantix AI (anchor tenant, 78 MW IT)
- Quantity
- 12 units
- MW served
- 36 MW
- Factory
- Pune, IN
- Quoted lead time
- 60 weeks
- Commercial value
- Data required
- Current stage
- TENDER
- Manufacturing start
- NA
- FAT date
- NA
- SAT date
- NA
Milestone chain
Award / PO
2027-01-22
Ship
2028-03-17
On site
2028-05-12
Energization
Q4 2028
SOURCE Industry contactLEVEL D · Market intelligenceLAST VERIFIED 2026-04-08LOW