40 MVA, 110/20 kV
Grid transformers · USD 9.6M (indicative)
132wCRITICAL
- Supplier
- Nordpower Transformers
- Project
- Rheinland AI Cluster
- End user
- Undisclosed EU hyperscaler (LOI, 46 MW IT)
- Quantity
- 2 units
- MW served
- 60 MW
- Factory
- Vaasa, FI
- Quoted lead time
- 132 weeks
- Commercial value
- USD 9.6M (indicative)
- Current stage
- TENDER
- Manufacturing start
- NA
- FAT date
- NA
- SAT date
- NA
Milestone chain
Award / PO
2026-09-14
Ship
2029-03-26
On site
2029-04-23
Energization
Q3 2029
SOURCE Manufacturer quotation 2026-07-28LEVEL A · Verified directLAST VERIFIED 2026-07-28HIGH