1000+ TR chillers + dry coolers
Chillers for 30% air-cooled load · Data required
42wCONSTRAINED
- Supplier
- Cryomax Heat Rejection
- Project
- Rheinland AI Cluster
- End user
- Undisclosed EU hyperscaler (LOI, 46 MW IT)
- Quantity
- 6 units
- MW served
- 14 MW
- Factory
- Milan, IT
- Quoted lead time
- 42 weeks
- Commercial value
- Data required
- Current stage
- TENDER
- Manufacturing start
- NA
- FAT date
- NA
- SAT date
- NA
Milestone chain
Award / PO
2028-03-13
Ship
2029-01-01
On site
2029-01-22
Energization
Q3 2029
SOURCE Analyst researchLEVEL C · High-quality secondaryLAST VERIFIED 2026-05-21MEDIUM