Deployment package · demo record

2.5 MW L2L CDU

Liquid cooling (70% DLC scope) · USD 5.9M (indicative)
20wNORMALTENDER
End user
Undisclosed EU hyperscaler (LOI, 46 MW IT)
Quantity
14 CDUs
MW served
32 MW
Quoted lead time
20 weeks
Commercial value
USD 5.9M (indicative)
Current stage
TENDER
Manufacturing start
NA
FAT date
NA
SAT date
NA

Milestone chain

Award / PO
2028-08-07
Ship
2028-12-25
On site
2029-01-29
Energization
Q3 2029
SOURCE Supplier confirmationLEVEL A · Verified directLAST VERIFIED 2026-08-05VERY HIGH