Equipment category intelligence · Power
Large Power Transformers
Primary constraint: GOES steel & bushing capacity. Expected improvement 2029+. Manufacturing concentrated in EU, KR, TR, IN, US.
148wCRITICAL94CRITICAL
- Current lead time
- 148 weeks
- 3 months ago
- 142 weeks
- 6 months ago
- 136 weeks
- 12 months ago
- 118 weeks
- Qualified manufacturers
- 14
- Credible alternatives
- 3
- Manufacturing regions
- EU, KR, TR, IN, US
- Shortage risk
- 94/100
SOURCE Manufacturer quotations (n=6)LEVEL A · Verified directLAST VERIFIED 2026-07-28HIGH
Lead-time history — never overwritten
118w
Aug 25
126w
Nov 25
136w
Feb 26
142w
May 26
148w
Aug 26
Manufacturers tracked (0)
No manufacturer record captured for this category yet.
Factories serving this category
Factory mapping for this category is incomplete.
Open capacity
No open slot recorded for this category.
Latest signals
Transformer core steel allocation tightened for 2027 slots
Multiple OEMs · 2026-08-02