Jurong Liquid-Cooled Node
Jurong, Singapore · Straits Compute · Procurement
Campus / IT
20 / 16 MW
Target RFS
Q2 2028
Forecast
Q2 2028
Readiness
81%
- Critical path
- MV switchgear
- Cooling architecture
- Full DLC
- End user
- Straits Compute (own capacity) + undisclosed cloud tenant
- Customer type
- Regional cloud / inference operator
- Workload / density
- Inference + fine-tuning, 100 kW/rack full DLC
- Offtake
- 60% self-use, 40% contracted colocation
- Utility / grid
- SP PowerGrid — 66 kV, allocation under IMDA DC-CFA
- Substation installed
- 2 × 20 MVA (40 MVA installed)
- EPC / main contractor
- Kajima Overseas Asia (main contractor)
- Location
- Singapore
SOURCE Client project briefLEVEL A · Verified directLAST VERIFIED 2026-08-03VERY HIGH
Phased deployment
Phase 110 MWQ2 2028Procurement
Phase 210 MWQ4 2028Detailed design
Supplier packages (4)
| Supplier | Equipment | Qty | MW | Factory | Award | Energization | Stage | |
|---|---|---|---|---|---|---|---|---|
| Arcline Power Systems | 22 kV switchgear line-ups, 2500 A | 2 line-ups | 20 | Houston, US | 2026-05-11 | Q2 2028 | IN PRODUCTION | Open |
| Thermaflux Liquid Cooling | 2.5 MW L2L CDU + cold plates + QDs | 8 CDUs (N+1) | 16 | Taoyuan, TW | 2026-07-06 | Q2 2028 | IN PRODUCTION | Open |
| Modulus Infrastructure | 5 MW integrated block, DLC + rear-door hybrid | 4 modules | 20 | Johor, MY | 2026-06-29 | Q2 2028 | AWARDED | Open |
| Voltbank Energy Storage | 1.5 MW UPS modules, UL 9540A cells | 16 modules | 20 | Ulsan, KR | 2027-01-11 | Q2 2028 | Open |